Gateway Hills Restaurant Update
May 1-May 5, 2017
Last week’s progress on the Restaurant Site @ Gateway Hills. See what was done last week at +Gateway Hills Bar & Grill.May 1, 2017
Backfilling primary utility trenches.
Backfilling primary utility trenches.
Backfilling secondary utility trenches.
Excavation for primary roof drains.
Excavation for primary roof drains.
Excavation for secondary power inside of building.
Grounding wires installed in preparation for transformer pad.
Conduits installed into building from transformer.
New poles are on the right side.
Building forms for retaining wall footings, installation of rebar for footings and peirs.
Setting grade pitch of pipe alongside Hiltz.
May 2, 2017
Backfilling of primary & secondary trenches.
Installing grade stakes for front walkway.
Strip forms from footings. Building forms for retaining wall, installing rebar & foundation ties.
Installing primary roof drain pipe.
Installing primary roof drain pipe.
May 3- May 4, 2017
Excess fill cleanup. Gravel & fabric installed up to top of footing. Final grade & compact of primary & secondary trenches.
Strip forms from walls.
Strip forms from walls.
Installing conduit & sweeps to pole.
Installing pull box for secondaries outside of building. Connecting conduits through foundation wall.
Setting transformer pad.
May 5, 2017
Backfilling of interior trenches.
Backfilling of interior trenches.
Visit:http://www.gateway-hills.com/new-restaurant-site/
Follow our progress blogs here:http://gatewayhills.blogspot.com/
Like us on Facebook: Gateway Hills
Follow us on Twitter: @GatewayHills
Follow us on LinkedIn: The John Flatley Company
Like us on Instagram: Gateway Hills
Follow us on Pinterest: GatewayHills
No comments:
Post a Comment