"Coring foundation & Core Drilling" at Restaurant Site, Gateway Hills

Gateway Hills Restaurant Update

April 24-April 28, 2017

Last week's progress on the Restaurant Site @ Gateway Hills. See what was done last week at +Gateway Hills Bar & Grill.



April 24-25
Grading of retention pond, Irrigation stone placed around outlet structure (seen above and below).

April 26 

Saw cutting for primary distribution from pole to transformer.

Spreading loam (seen above and below).

 

Removing faulty trenching patch & reinstalling.
April 27 

Trenching for primary.
Excavating for transformer pad.
Excavating for core drilling.
Saw cutting for secondary trenching.
(Seen in below 3 images).


 

Coring foundation for secondaries, phone, and cable into building (seen above and below).

 
April 28

Trenching for secondaries, spreading sand for conduits at base of trench.

Installing remaining ipe siding at entryway.

Installing conduit & sweeps for primary, phone, & cable (seen above and below).

 
We are still looking for a restaurant operator for this 7,500 SF restaurant space for lease. If you know someone looking to open in a new location, call us today: 603-598-7500!Want to know more?

 Visit:http://www.gateway-hills.com/new-restaurant-site/
Follow our progress blogs here:http://gatewayhills.blogspot.com/
 
Like us on Facebook: Gateway Hills
Follow us on Twitter: @GatewayHills
Follow us on LinkedIn: The John Flatley Company
Like us on Instagram: Gateway Hills
Follow us on Pinterest: GatewayHills



No comments:

Post a Comment