We have made a lot of progress thus far on our Restaurant Site @GatewayHills. Check out what we have completed last week at +Gateway Hills Bar & Grill.
April 17, 2017
Uncovering ledge under the future patio.
Excavating for site lighting conduit installation.
Excavating for site lighting conduit installation.
Excavating for site lighting conduit installation.
April 18, 2017
Excavation for remaining conduit for site lighting.
Excavation for remaining conduit for site lighting.
Excavating around ledge before it is hammered out (seen above and below).
Backfilling complete for site lighting pictured above.
Installing duct drops into RTU curbs.
April 20, 2017
Dumpster pad prep – 6 bollards will be set in concrete along the back of the enclosure.
Ledge removal underway. Hammered and trucked off site.
Elevation markers are set in place for retention pond.
RTU’s installed, two curbs for future use temporarily covered.
Preparation of trenches for patio & retaining wall.
Layout & prepping for sidewalks.
Drain pipe for primary roof drain connected into catch basin.
We are still looking for a restaurant operator for this 7,500 SF restaurant space for lease. If you know someone looking to open in a new location, call us today: 603-598-7500!