Friday, March 24, 2017

'Vinyl Installation Started' at Restaurant Site, Gateway Hills

Restaurant Update March 20-24

A lot of work was completed this week at our Restaurant Site +Gateway Hills Bar & Grill

Here’s an update on what was completed this week:

 
 
 
 
Southwest wall: Zip tape is installed long wall sheathing seams.


 
 
 
Northeast wall: Vinyl installation in progress on rear of building.

 
 
Northeast wall: Vinyl installation in progress on rear of building. Vinyl around door will be finished after door installation.  
 
 
 
Southwest wall: Aluminum channel installed around main entryway in preparation for IPE siding installation.
 
 
 
Southwest wall: Close-up of storefront channel
 
 
 
Gas utility markings showing location of trenching from street.
 
 
 
Gas utility markings showing location of trenching across Innovative Way.
 
 
 
Setting & marking final locations for roof curbs & blocking
 
 
 
Cutting of concrete foundation wall in preparation for storefront entryway for patio.
 


We are still looking for a restaurant operator for this 7,500 SF restaurant space for lease. If you know someone looking to open in a new location, call us today: 603-598-7500!